Twenty-six turbines will be installed along the coast of Jeolla Meridionale province. The state-funded funds will cover about 40% of the total investment. According to reports from the Korea Times, an installation capacity of 390 megawatts for the Shinan UI project will rise at the Sinan National Sports Center.

Minister of Climate, Energy and Environment Kim Sung-hwan defined Shinan UI as the first large-scale offshore wind power plant supported by domestic capital alone. He stated that this initiative was crucial both for securing clean energy for future digital activities and consolidating the country's industrial ecosystem. A significant portion of resources comes from financial tools sustained by public sector funding.

Shinan UI was chosen as the first investment of the National Growth Fund, which is backed by the State. According to the Korea Times, government intervention into the structure finances aims to guarantee more stability on the project and allow work commencement within expected timeframes. The rest of the investment falls under a coalition of national capital described by the source, but no detailed breakdown of other resources or economic conditions mentioned either.

This park will consist of 26 turbines each with a power output of 15 megawatts. Once completed it should produce 1,062 gigawatt-hour of clean electricity every year. Government estimates support that such production would be sufficient enough to feed approximately 300,000 households plus contribute to electric supply of programmed industries in the region.

Potential targets include data centers dedicated to artificial intelligence and semiconductor fabrication sites planned in the area. The government links construction of the facility not only to expansion of renewable sources but also availability of stable supply for digital infrastructure and manufacturing characterized by high energy consumption. Construction will be guided by an alliance of Korean core companies.

The Korea Times mentions Hanwha Ocean, SK eternix and Hyundai Engineering & Construction among involved enterprises. Use of domestic operators combined with internal resource backing constitutes central element of this project strategy. Commercial operation date set at January 2029 leaves consortium several years timeline for building and installing turbines in sea.

No details provided regarding intermediate stages of site construction, scheduled completion dates for individual works or connection progress between aerogenerators and grid. Shinan UI represents concrete start of South Korea's attempt to build large-scale offshore wind farm using finance and industry national backing. Further checks required during execution on cost and time announced, as well as actual capacity reached by installation expected to meet estimated annual production.

First operational reference mentioned is commercial commencement date set at January 2029.